Numéro |
Nom |
Date |
Temps |
Nb. Pers. |
Etendu |
|
|
1A |
Installation of under carriage & strut carry through |
02/03/23 |
1.0 |
3 |
3.0 |
|
2A |
Installation & assembly of front rudder pulley |
02/03/23 |
1.0 |
3 |
3.0 |
|
3A |
Installation of axle tube |
02/03/23 |
1.0 |
3 |
3.0 |
|
4A |
Installation of under carriage corner brackets |
02/03/23 |
1.0 |
3 |
3.0 |
|
5A |
Installation of strut attach plates |
02/03/23 |
1.0 |
3 |
3.0 |
|
|
6A |
Installation of floor tube channels |
02/04/04 |
0.8 |
3 |
2.3 |
|
7A |
Installation of down tube channels |
02/03/25 |
0.7 |
2 |
1.3 |
|
7B |
Installation of window plate |
02/03/25 |
0.7 |
2 |
1.3 |
|
7C |
Installation of root tube assembly to down tube |
02/03/25 |
0.7 |
2 |
1.3 |
|
8A |
Installation of leading edge channel |
02/03/26 |
0.3 |
3 |
0.8 |
|
9A |
Installation of post plate |
02/03/26 |
0.3 |
3 |
0.8 |
|
10A |
Installation of seat belt plate & bottom wing channel |
02/03/26 |
0.3 |
3 |
0.8 |
|
11A |
Installation of pylon rear brace |
02/03/26 |
0.3 |
3 |
0.8 |
|
12A |
Installation of seat belt & wing channel bottom bolt |
02/03/26 |
0.3 |
3 |
0.8 |
|
13A |
Installation of pylon side & cabin side channels |
02/03/26 |
0.3 |
3 |
0.8 |
|
14A |
Installation of pylon side & belly rib |
02/04/04 |
0.5 |
3 |
1.5 |
|
15A |
Installation of top pylon channels |
02/03/28 |
1.4 |
4 |
5.5 |
|
16A |
Installation of pylon diagonals |
02/03/28 |
1.4 |
4 |
5.5 |
|
16A |
Installation of pylon diagonals |
02/04/04 |
0.1 |
3 |
0.3 |
|
17A |
Installation of pylon braces |
02/04/04 |
1.7 |
3 |
5.0 |
|
17A |
Installation of pylon braces |
02/04/05 |
0.5 |
2 |
1.0 |
|
17A |
Installation of pylon braces |
02/04/06 |
1.5 |
3 |
4.5 |
|
17A |
Re-Installation of gusset holding firewall |
02/05/25 |
2.0 |
1 |
2.0 |
|
18A |
Installation of main wheels |
02/04/05 |
2.5 |
2 |
5.0 |
|
18A |
Installation of main wheels |
02/04/06 |
2.0 |
2 |
4.0 |
|
19A |
Installation of fabric support plates |
02/04/06 |
2.5 |
2 |
5.0 |
|
20A |
Installation of lexan braces |
02/04/06 |
0.5 |
1 |
0.5 |
|
21A |
Installation of rear floor pan |
02/04/06 |
2.0 |
1 |
2.0 |
|
22A |
Installation of seats |
02/04/06 |
0.8 |
3 |
2.3 |
|
23A |
Installation of front seat belt |
02/04/07 |
0.5 |
2 |
1.0 |
|
23B |
Installation of rear seat belt |
|
|
|
0.0 |
|
24A |
Installation of rear instrument panel |
02/04/07 |
0.8 |
2 |
1.5 |
|
25A |
Installation of flaperon trim adjuster handle & rod |
02/04/07 |
0.5 |
2 |
1.0 |
|
25A |
Installation of flaperon trim adjuster handle & rod |
|
|
|
|
|
26A |
Installation of differential plate & slider |
|
|
|
0.0 |
|
27A |
Assembly of rear control stick (1 of 2) |
02/05/18 |
0.5 |
2 |
1.0 |
|
27B |
Assembly of rear control stick (2 of 2) |
02/05/18 |
0.5 |
2 |
1.0 |
|
27C |
Installation of rear control stick |
02/05/18 |
0.1 |
2 |
0.2 |
|
28A |
Assembly of front control stick (1 of 2) |
02/05/20 |
0.7 |
1 |
0.7 |
|
28B |
Assembly of front control stick (2 of 2) |
02/05/21 |
0.3 |
2 |
0.7 |
|
29A |
Installation of front control stick |
02/05/21 |
0.2 |
2 |
0.4 |
|
30 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
31A |
Installation of aileron control cables (1 of 2) |
|
|
|
0.0 |
|
31B |
Installation of aileron control cables (2 of 2) |
|
|
|
0.0 |
|
32A |
Assembly of floor cross tubes to floor tube |
02/04/07 |
1.0 |
3 |
3.0 |
|
33A |
Installation of floor tube assembly |
02/04/07 |
0.2 |
3 |
0.6 |
|
34A |
Installation of rudder return pulley |
02/04/07 |
0.4 |
3 |
1.2 |
|
35A |
Installation of front window tubes |
02/04/07 |
1.6 |
2 |
3.2 |
|
35A |
Installation of front window tubes |
02/04/08 |
2.5 |
2 |
5.0 |
|
36A |
Installation of front floor pan |
02/04/09 |
2.0 |
3 |
6.0 |
|
37A |
Installation of cabin brace |
02/04/09 |
1.0 |
3 |
3.0 |
|
37A |
Installation of cabin brace |
02/04/15 |
3.0 |
2 |
6.0 |
|
38A |
Installation of front rudder pedals |
02/04/08 |
1.5 |
1 |
1.5 |
|
38A |
Installation of front rudder pedals |
02/04/15 |
3.0 |
2 |
6.0 |
|
39A |
Installation of back rudder pedals |
|
|
|
0.0 |
|
40A |
Installation of cable attachment tangs |
|
|
|
0.0 |
|
41A |
Installation of front instrument panel |
|
|
|
0.0 |
|
42A |
Installation of elevator tail plate anchor nuts (1 of 2) |
02/03/31 |
0.8 |
3 |
2.3 |
|
42B |
Installation of elevator tail plate anchor nuts (2 of 2) |
02/03/31 |
0.8 |
3 |
2.3 |
|
43A |
Installation of rudder bearing & sleeve |
02/04/01 |
2.3 |
2 |
4.5 |
|
44A |
Installation of elevator assembly |
02/04/01 |
0.3 |
3 |
0.8 |
|
44A |
Installation of elevator assembly |
02/05/18 |
0.8 |
2 |
1.5 |
|
45A |
Installation of elevator cables |
02/05/18 |
0.6 |
2 |
1.2 |
|
45A |
Installation of elevator cables |
02/05/21 |
0.4 |
2 |
0.8 |
|
47A |
Installation & assembly of elevator cable pulley |
02/05/23 |
4.0 |
1 |
4.0 |
|
47A |
Installation & assembly of elevator cable pulley |
02/05/25 |
3.0 |
2 |
6.0 |
|
48A |
Rudder, horn & tail wheel assembly |
02/04/20 |
0.8 |
2 |
1.5 |
|
49A |
Installation of the fin leading edge |
02/04/20 |
0.8 |
2 |
1.5 |
|
50A |
Installation of fin T.E. bracket |
02/04/20 |
0.5 |
2 |
1.0 |
|
50B |
Installation of fin on T.E. |
02/04/20 |
0.8 |
2 |
1.5 |
|
51A |
Installation of fin brace |
02/04/21 |
0.6 |
2 |
1.3 |
|
51B |
Installation of leading edge brace |
02/04/21 |
0.6 |
2 |
1.3 |
|
52A |
Installation of rudder cables & rudder return bungee |
|
|
|
0.0 |
|
53A |
Installation of rudder horn |
02/04/20 |
0.8 |
2 |
1.5 |
|
54A |
Installation of rudder cable & rudder return bungee |
|
|
|
0.0 |
|
55A |
Installation of rudder pulley & brackets |
|
|
|
0.0 |
|
56A |
Installation of rudder cable guides |
|
|
|
0.0 |
|
57A |
Installation of stabilizer spacer |
|
|
|
0.0 |
|
57B |
Installation of stabilizers |
|
|
|
0.0 |
|
58A |
Installation of elevator control cables |
|
|
|
0.0 |
|
59 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
60A |
Installation & assembly of push pull tube |
|
|
|
0.0 |
|
61A |
Installation of wing ribs (Right Wing) |
02/03/30 |
2.3 |
3 |
6.8 |
|
62A |
Installation of rib support channels
(Right Wing) |
02/03/30 |
2.3 |
3 |
6.8 |
|
62B |
Installation of fabric support chanels
(Right Wing) |
02/06/08 |
1.0 |
2 |
2.0 |
|
63A |
Installation of wing gap pipe & wing bow (Right Wing) |
02/03/31 |
1.3 |
3 |
3.9 |
|
61A |
Installation of wing ribs (Left Wing) |
02/03/31 |
1.3 |
3 |
3.9 |
|
62A |
Installation of rib support channels (Left Wing) |
02/03/31 |
1.3 |
3 |
3.9 |
|
62B |
Installation of fabric support chanels (Left Wing) |
02/06/08 |
3.0 |
1 |
3.0 |
|
63A |
Installation of wing gap pipe & wing bow (Left Wing) |
02/03/31 |
1.3 |
3 |
3.9 |
|
|
Pre-Cover Inspection by Pierre Marcotte (MD-RA) |
01/05/15 |
1.5 |
4 |
6.0 |
|
|
Construction des tubes d'embarcation |
02/05/23 |
7.0 |
1 |
7.0 |
|
|
Construction du Firewall |
02/05/24 |
5.0 |
2 |
10.0 |
|
|
Construction du Firewall |
02/05/25 |
3.0 |
1 |
3.0 |
|
|
Removal of cables, elevator and rudder for covering |
02/05/25 |
0.5 |
2 |
1.0 |
|
|
Covering of Rudder and Fin |
02/06/15 |
5.5 |
3 |
16.5 |
|
|
Covering cabin underbody and 1 side |
02/07/07 |
4.0 |
2 |
8.0 |
|
|
Covering cabin underbody and flaperon |
02/07/13 |
5.0 |
3 |
15.0 |
|
|
Covering flaperon |
02/07/19 |
4.0 |
2 |
8.0 |
|
|
Covering other flaperon |
02/07/21 |
3.5 |
2 |
7.0 |
|
|
Finishing tape flaperon #1 |
02/08/01 |
1.5 |
1 |
1.5 |
|
|
Finishing tape cockpit & vertical Stabiliser |
02/08/05 |
3.0 |
2 |
6.0 |
|
|
preparation of in-wing fuel tanks |
02/08/05 |
1.0 |
2 |
2.0 |
|
|
Inspection of in-wing fuel tanks |
02/08/20 |
2.0 |
3 |
6.0 |
|
|
Installation of nav lights wiring & in wing tank right wing |
02/08/25 |
4.0 |
3 |
12.0 |
|
|
Covering bottom of right wing |
02/08/26 |
4.0 |
3 |
12.0 |
|
|
Covering bottom of right wing |
02/08/31 |
5.0 |
2 |
10.0 |
|
|
Installation of in wing tank right wing |
02/08/31 |
3.5 |
3 |
10.5 |
|
|
Covering top of right wing |
02/08/31 |
3.5 |
3 |
10.5 |
|
|
finishing sides right wing |
02/09/01 |
1.0 |
1 |
1.0 |
|
|
Finishing tape on bow of right wing |
02/09/06 |
2.0 |
1 |
2.0 |
|
|
Finishing trailing edge of right wing |
02/09/07 |
2.0 |
1 |
2.0 |
|
|
Finishing tape right wing |
02/09/08 |
4.0 |
1 |
4.0 |
|
|
Preparation of left wing |
02/09/08 |
4.0 |
3 |
12.0 |
|
|
Covering bottom of left wing |
02/09/10 |
4.0 |
3 |
12.0 |
|
|
Covering top of left wing |
02/09/14 |
4.0 |
2 |
8.0 |
|
|
Finishing tape trailing edge of left wing |
02/09/15 |
2.0 |
1 |
2.0 |
|
|
Finishing tape trailing edge of left wing |
02/09/16 |
1.3 |
2 |
2.5 |
|
|
End edge and ribs |
02/09/20 |
2.0 |
2 |
4.0 |
|
|
Inspection rings, drain grommets |
02/10/12 |
9.0 |
4 |
36.0 |
|
|
Test de peinture sur echantillons |
03/03/30 |
5.0 |
3 |
15.0 |
|
|
Primer stabilisateur horizontal, rudder elevator |
03/05/03 |
6.0 |
4 |
24.0 |
|
|
Topcoat stabilisateur horizontal, rudder elevator |
03/05/04 |
4.0 |
3 |
12.0 |
|
|
Installer et nettoyer les ailes |
03/05/10 |
8.0 |
3 |
24.0 |
|
|
Primer ailes |
03/05/10 |
4.0 |
4 |
16.0 |
|
|
Topcoat ailes |
03/05/11 |
4.5 |
3 |
13.5 |
|
|
Preparation cabine et ailerons |
03/05/17 |
6.0 |
4 |
24.0 |
|
|
Primer cabine et ailerons |
03/05/18 |
5.0 |
4 |
20.0 |
|
|
Topcoat cabine et ailerons |
03/05/19 |
7.5 |
3 |
22.5 |
|
65A |
Installation of motor mount channels (type E drive) |
02/04/21 |
0.5 |
3 |
1.5 |
|
66A |
Installation of motor mount channels (type C drive) |
|
|
|
0.0 |
|
67A |
Installation of front & rear strut attach brackets (1 of 2) |
|
|
|
0.0 |
|
67B |
Installation of front & rear strut attach brackets (2 of 2) |
|
|
|
0.0 |
|
68A |
Installation of wings |
|
|
|
0.0 |
|
68B |
Front strut attachment |
|
|
|
0.0 |
|
69A |
Rear strut attachment |
|
|
|
0.0 |
|
70 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
71A |
Level root tube for washout adjustment |
|
|
|
0.0 |
|
71B |
Washout setting |
|
|
|
0.0 |
|
71C |
Washout adjuster assembly |
|
|
|
0.0 |
|
72A |
Locking the strut attach tubes (1 of 2) |
|
|
|
0.0 |
|
72B |
Locking the strut attach tubes (2 of 2) |
|
|
|
0.0 |
|
73A |
Installation of jury struts (1 of 2) |
|
|
|
0.0 |
|
73B |
Installation of jury struts (2 of 2) |
|
|
|
0.0 |
|
74 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
75A |
Installation of ailerons (1 of 2) |
03/05/17 |
0.3 |
1 |
0.3 |
|
75A |
Installation of ailerons (1 of 2) |
|
|
|
0.0 |
|
75B |
Installation of ailerons (2 of 2) |
|
|
|
0.0 |
|
75C |
Installation of ailerons control rods |
|
|
|
0.0 |
|
76A |
Installation of aileron gap seal |
|
|
|
0.0 |
|
77A |
Installation of front & front side windows |
|
|
|
0.0 |
|
77B |
Installation of middle side windows |
|
|
|
0.0 |
|
77C |
Installation of rear right side windows |
|
|
|
0.0 |
|
78 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
79A |
Installation of front doors (1 of 2) |
|
|
|
0.0 |
|
79B |
Installation of front doors (2 of 2) |
|
|
|
0.0 |
|
80A |
Installation of front door latch |
|
|
|
0.0 |
|
81 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
82A |
Installation of rear door (1 of 2) |
|
|
|
0.0 |
|
82B |
Installation of rear door (2 of 2) |
|
|
|
0.0 |
|
83A |
Installation of pylon side wing cover |
|
|
|
0.0 |
|
83B |
Installation of center wing cover |
|
|
|
0.0 |
|
84A |
Installation of rear shroud |
|
|
|
0.0 |
|
85A |
Installation of U/C brace tube |
03/05/15 |
0.3 |
1 |
0.3 |
|
86A |
Installation of engine & mounts (type E drive) |
|
|
|
0.0 |
|
87A |
Installation of engine & mounts (type C drive) |
|
|
|
0.0 |
|
88 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
89 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
90 |
N/A this step does not have a drawing |
|
|
|
0.0 |
|
91A |
Installation of rudder & elevator trim tabs |
|
|
|
0.0 |
|
92A |
Installation of tail braces |
|
|
|
0.0 |
|
93 |
|
|
|
0.0 |
|
94 |
|
|
|
0.0 |
|
95A |
Installation of fuel tanks |
|
|
|
0.0 |
|
|
Wiring schematic for chinook plus |
|
|
|
0.0 |
|
|
|
|
|
|
|
Total |
|
232.8 |
|
590.3 |
|
|
Proportion des étapes faites |
|
65% |
|
|
|
Proportion des 200 heures déjà faites |
|
295% |
|
|
|
|
|
|
Total des heures personnes |
|
590.3 |
|
|
|
Dernière mise-à-jour |
|
23-May |
|
|
|
|
|
|
|
|
|
|